As said nearly there, van dried out, replaced rotten timber, treated existing timbers locally, replaced polystyrene just the wallboard and furniture to put back on the inside,awning rail (rear half) removed, cleaned and back on with new sealant.
The rail was a nightmare to do, spent nearly 22 hours on that!! but it looks good and I know its sealed properly.
I WILL be away for Easter--hip hip hooray--
The rail was a nightmare to do, spent nearly 22 hours on that!! but it looks good and I know its sealed properly.
I WILL be away for Easter--hip hip hooray--